This document describes considerations and requirements of payment for temporary traffic control (TTC). The document offers several recommended methods and presents the advantages and disadvantages of each. Also addressed are techniques the agency and the contractor can use to monitor the effectiveness of selected methods.
This document is organized into the following sections:
The idea of using performance-based specifications for TTC in work zones is relatively new. One of the major challenges for moving towards performance-based specifications in this area is the lack of data and equipment available to verify compliance. In the first example above, devices for measuring sign retroreflectivity are fairly costly and require personnel trained on how to properly calibrate and use the devices. Most agencies and contractors do not have these devices in sufficient quantities, which would make it difficult to assess or enforce compliance with such a specification. Similarly, a maximum tolerable delay specification would require equipment to measure travel times at the necessary frequency.
In contrast, unit price payment should be provided for those items for which the contractor has little or no control over the quantity and no firm estimate of quantities is provided in the PS&Es, but for which the highway agency has control of the actual quantity to be required during the project. Furthermore, the payment should be limited to those items actually required by the agency; items (such as the movement of barrier) that exist or are performed for the convenience of the contractor would not be appropriate for payment.
Table 1 summarizes the key advantages and disadvantages of lump sum and unit price pay items for temporary traffic control. Lump sum pay items tend to be simpler to use, especially for low-cost projects, and is believed to reduce agency workload to document item usage in the project. However, the use of lump sum for pay items makes the agency TTC review contractual rather than approval related because the plan is tied to the number of items that will be used. Consequently, any significant changes to the TTC quantities during the project will
require additional administrative efforts by the agency to modify the contract and increase or decrease the lump sum amount.
* For example, having multiple portable changeable message signs (PCMS) in a project displaying “DRIVE SAFELY” messages so that daily use rental of each PCMS can be collected.
Conversely, the use of unit pay items does offer increased flexibility in the amount of temporary traffic control that is to be used, which can be beneficial on highly-complex projects where field changes may be more common. This increased flexibility does increase agency manpower requirements to monitor and document TTC device usage on a continuous basis. In addition, the use of unit pay items may encourage the overuse of some devices in order to increase payment, and so must be carefully managed by the agency.
Regardless of the basis used for pay items, the specifications and other PS&E documents should provide sufficient details so that the quantity and types of devices required to be compliant with agency standards, and the overall effort required to implement and maintain the TMP, can be determined. Specifications should also clearly indicate how placement, movement/relocation, and maintenance of traffic control devices and safety features will be compensated. Finally, the specifications should include provisions to require and enforce contractor compliance with the contract provisions relative to implementation and maintenance of the project TMP and related traffic control items. Enforcement provisions may include remedies such as liquidated damages, work suspensions, or withholding payment for noncompliance.
Conversely, mobilization costs and the cost of maintaining temporary traffic control over the life of a project are highly dependent upon contractor and subcontractor decisions and practices (i.e., who is responsible, how it is accomplished, etc.). As a result, these types of costs are almost always bid on a lump sum basis.
Table 2. Typical Treatment of Temporary Traffic Control and Safety Items
How Can I Locate More Information Regarding This Topic?
Lump Sum Traffic Control. Washington State Department of Transportation.
Available at http://www.wsdot.wa.gov/Projects/delivery/alternative/LumpSum.htm
Johnson, A., L. Rue, T. Burch, and D. Clark. Work Zone Traffic Control:
Survey of Contracting Techniques. In Public Roads, Vol. 64, No. 6, May/June 2001. Available at http://www.fhwa.dot.gov/publications/publicroads/01mayjun/traficcontrol.cfm
Infrastructure Design Directive IDD-2009-04 (Estimates and Lump Sum Pricing Guidelines). New Mexico Department of Transportation, June 26,2009. Available at
http://www.nmshtd.state.nm.us/upload/images/Contracts_Unit/IDD-2009-04.pdf
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects. U.S. Department of Transportation, Federal Highway Administration. 1996. Available at http://www.efl.fhwa.dot.gov/design/manual/Fp96.pdf
Quality Guidelines for Temporary Traffic Control Devices. American Traffic Safety Services Association. Available at http://www.atssa.com/cs/roadway-safety-store
Developed By:
The Roadway Safety Consortium
202‐628‐5465
www.workzonesafety.org
Laborers’ International Union of North America
Laborers’ Health and Safety Fund of North America
LIUNA Training and Education Fund
American Road and Transportation Builders Association
National Asphalt Pavement Association
International Union of Operating Engineers
American Association of State Highway
and Transportation Officials
Texas Transportation Institute
FOF Communications
US Department of Transportation Federal Highway Administration
This material is based upon work supported by the Federal Highway Administration under Grant Agreement No. DTFH61‐06‐G‐00007.
Any opinions, findings and conclusions or recommendations expressed in this publication are those of the author(s) and do not necessarily reflect the view of the Federal Highway Administration. This publication does not constitute a national standard, specification or regulation.
VALID HTML
VALID CSS
508 WAI